Christiana Care Bone Marrow Air Handling Unit Replacement
In the penthouse, two existing air handling units are located in an area that is not conducive for conventional replacement. The access to the units is extremely difficult. The existing units were dismantled and the new units were installed panel by panel.
Products Used: Air Enterprises SiteBilt Units
Results: As one of the existing units was operational for the critical environment, the second air handling unit was removed. The Air Enterprises/subcontractor Sitebilt team erected the unit in the penthouse panel by panel. Each piece was installed with the same quality of a factory constructed unit. Both units were installed within the required schedule and the Bone Marrow Critical Area was never disrupted during construction.